East Feliciana Homebuilding: Buying the Permit Does Not End Plan Review
East Feliciana Parish’s published new-home procedure contains an easy-to-miss warning: although a builder may purchase the permit before review, the permit does not become valid until plan review is complete. The same document says to allow a minimum of two weeks for plan review. That makes pre-construction paperwork part of the land and financing timeline.

Photo: Galen Parks Smith, Wikimedia Commons, licensed under CC BY-SA 3.0.
Several items come before plan review
The parish procedure calls for property divisions and zoning to be completed and approved by the Police Jury or applicable municipality before the plan-review and permitting process begins. It also calls for the 911 address to be obtained or verified and for a parish floodplain determination.
If the property is in a flood zone, the procedure requires a completed and stamped elevation certificate from a licensed surveyor, engineer or architect. The official sequence also identifies a completion elevation certificate after the slab is poured and before framing on the slab begins.
The survey must support the building plan
The permit package calls for proof of ownership, a survey map and a plot plan derived from a legal plat or survey. The plot plan must show drainage, utility and private servitudes, required building lines, setbacks to the property lines and the size and placement of the driveway.
That is why a buyer should not choose a house footprint from acreage alone. Servitudes, access, flood elevation and setbacks can shift the buildable area even when the tract has ample total square footage.
Plans and contractors are part of feasibility
East Feliciana’s procedure requires house-plan information covering foundation, floor, roof, elevations, plumbing, electrical and HVAC layouts, doors, windows and square footage. It also addresses state licensing and parish registration for contractors and trades.
An owner-builder exemption is not simply a verbal choice. The parish document describes a signed and notarized affidavit claiming exemption from licensure that is recorded with the Clerk of Court. Buyers considering that route should confirm current requirements and discuss insurance, lending and liability with the appropriate professionals.
Put the sequence into the purchase contract
When a land purchase depends on a new home, the inspection or feasibility period should allow time to assemble the address, flood determination, survey, utility information and concept plan before money is committed to final drawings or site work.
A useful checklist includes:
Written confirmation of jurisdiction and any town or village approval
Approved division or legal-lot status
Verified 911 address
Flood determination and required elevation work
Survey with servitudes, setbacks and driveway placement
Utility and wastewater feasibility
Plan-review timeline coordinated with closing and construction financing
A receipt is not authorization to build
The central distinction is simple: paying for the permit and completing plan review are different milestones. The parish says the permit becomes valid only after plan review is completed, and an approved set of plans must then remain at the job site.
Sellers should describe completed approvals accurately, and buyers should verify them directly. A prior owner’s concept, invoice or permit receipt should not be marketed as a currently buildable homesite without confirming the permit status, revision history and parcel conditions.
Talk through the property, not just the headline
Rural acreage and village or town property can follow different approval paths, so build the permit sequence around the exact parcel. Explore East and West Feliciana real estate. For property-specific guidance, contact Ryan Pritchard at Pritchard Real Estate or call 225-235-9509.
Sources
East Feliciana New Residential Construction Permitting Procedure
East Feliciana Inspections and Permits
East Feliciana New Residential Construction Permitting Procedure: https://efparish.org/wp-content/uploads/2024/01/RESIDENTIAL-PERMITTING-NEW-2.pdf
East Feliciana Inspections and Permits: https://efparish.org/inspections-and-permits/





Comments