top of page
East Feliciana Parish Courthouse in Clinton, Louisiana

East Feliciana’s Solar-Farm Ordinance Adds a Local Due-Diligence Layer for Large Tracts

Ryan Pritchard
1 day ago
2 min read

East Feliciana Parish Police Jury minutes show that the jury adopted Solar Energy/Solar Farm Permitting Ordinance No. 12-87 with four amendments on June 1, 2026. The adopted items address parish-road maintenance, a 200-foot setback, screening within the buffer and a decommissioning performance bond in favor of the landowner.

For owners of large tracts, the lesson is not that a solar project is approved for any particular site. It is that a private option or lease now sits alongside a defined local permitting layer that must be read before land is committed.

East Feliciana Parish Courthouse in Clinton, Louisiana
East Feliciana’s adopted solar-farm ordinance adds parish review to the private lease and state-level due-diligence process.

East and West Feliciana real estate — local property overview.

What the official minutes confirm

The road amendment places responsibility on the developer or project owner to maintain parish roads used by the project to Louisiana DOTD standards during construction, operation and through final decommissioning. Routes are to be identified before construction and submitted to the parish, which may identify additional roads.

The minutes also record a setback of not less than 200 feet from the proposed solar farm’s property line, a minimum 100-foot area of trees or shrubbery within the buffer, and a performance bond recorded in the parish records to support the landowner’s decommissioning plan.

Read the full ordinance, not only the meeting summary

Minutes document the action and amendments but are not a substitute for the complete ordinance, current application forms or later amendments. Obtain Ordinance 12-87 and confirm its definitions, fees, plan requirements, review sequence and enforcement provisions with the parish.

Verify whether a project footprint, substation, transmission line, access road or staging area is treated differently. A boundary-level setback can affect usable acreage even when panels occupy only part of a tract.

Put road and restoration obligations in the lease

A local ordinance may require the developer to perform, but the landowner’s contract should still address baseline road condition, construction traffic, dust, drainage, gates, timber removal, soil compaction and restoration. Define who documents damage and how disputes are resolved.

Decommissioning language should coordinate the parish requirement, the recorded performance bond and the private lease. Counsel should examine who controls the bond, how costs are updated and what happens after an assignment or operator default.

Separate option, permit and construction stages

An executed option may only give a developer time to study a site. Local permit approval, state review, interconnection and financing are separate steps. Avoid describing an optioned tract as an approved or under-construction solar farm unless the public record supports that status.

Owners should preserve ordinary land alternatives while an option is pending and understand any restrictions on sales, mortgages, hunting, timber, farming or improvements.

Property-specific next step

Ryan Pritchard can help organize the real-estate side of this investigation—parcel, access, intended use and transaction timing. Call 225-235-9509 or use the contact page, and consult the appropriate attorney, surveyor, engineer, insurer or public agency for final determinations.

Sources and photo credit

East Feliciana Parish June 1, 2026 meeting minutes — official adoption record for Ordinance 12-87.

East Feliciana building inspections and permits — current parish permit resource.

Photo: Galen Parks Smith via Wikimedia Commons — CC BY 2.5 (also offered under CC BY-SA 3.0).

Comments


bottom of page